Coate Water Care · Site 3

82-bedroom care home

Supply constraints made cutting peak demand the priority.

  • Solar PV
  • Battery
  • EV charging
Aerial view of a rural care home with long runs of solar panels across its roofs
01 / What was installed, and reported

Reported results
for this home.

Annual bill before£45,000
Annual bill after£14,000
Reported annual saving£31,000
Solar panels
273
Battery
50 kWh
EV charger
1
On site
About 3 weeks

Figures are the annual electricity bills of one client's three homes before and after installation. Results vary by site, usage and energy tariffs.

NoteReported figures, not independently verified.

02 / The roof

Slide across.
See the panels appear.

The same roof, before and after installation. Drag or use the arrow keys.
Design render of the care home buildings with the planned panel layout on each roofDesign render
The panel layout, modelled before work started.
03 / The challenge and the works

The challenge.

Supply constraints limited how much power the home could draw at any one time, so the priority was cutting peak demand.

The works.

  • Energy audit to find the most cost-effective upgrades
  • 273 solar panels across every suitable roof
  • 50 kWh battery storing surplus solar, and charging on cheaper off-peak rates in winter
  • Load shifting designed around an 80 A per-phase limit
  • 1 EV charger

NoteThe source reports a load-shifting limit of 80 A per phase at this site; it is a reported design target, not a universal limit.