Coate Water Care:
four care homes, one programme.

Solar PV, battery storage and EV charging for a family-run care group with over 25 years in care. We picked their four best sites and delivered them one after another, around three weeks each.

  • Solar PV
  • Battery
  • EV charging
Supplied project · Coate Water Care Ltd
Site 1 plant room after installation: inverters, a battery unit and isolators on a boarded wall
The programme
Four care homes, three detailed records
About three weeks per site
Family-run, over 25 years in care
01 / The results

The published results
in numbers.

Coate Water Care · 3 homes
Annual bills before£125,000
Annual bills after£33,000
Reported annual saving£92,000
Solar panels
698
Battery storage
150 kWh
EV chargers
5

Figures are the annual electricity bills of one client's three homes before and after installation. Results vary by site, usage and energy tariffs.

NoteTotals cover sites 1 to 3; the fourth home's records aren't complete yet. Site 1 includes the switch from electric radiators to renewable heating.

02 / The brief

Four goals.

  1. 01

    Comply with ESOS

    Meet their Energy Savings Opportunity Scheme obligations with real, measurable improvements.

  2. 02

    Cut their carbon footprint

    Lower emissions across their property portfolio.

  3. 03

    Rely less on the grid

    Generate and store electricity on site, so market price swings matter less.

  4. 04

    Reduce running costs

    Bring down electricity bills that were running at £35,000 to £45,000 a year per home.

NoteESOS requires an audit, reporting and an action plan, not installing renewables. Upgrades alone don't make an organisation compliant.

03 / Approach and delivery

Audit first.
Then one home after another.

Approach

We reviewed every site in the group and picked the best four to start with. Each one began with a full energy audit, so the design fitted how that home actually uses power.

Delivery

We then delivered the homes back to back. Each took around three weeks, everything went to plan, and residents and staff saw very little disruption while we were on site.

Site 1 plant room before installation: bare boarded walls with a small consumer unit and loose cablingBefore
Site 1 plant room, before.
Site 1 plant room after installation: inverters, a battery unit, isolators and documentation mounted neatlyAfter
Site 1 plant room, after.

Coate Water Care project walkthrough

A video space for the story behind the multi-site programme and the completed installations.

05 / In their words
“Creative Energy have supported our transition to ensuring our care homes are as sustainable as possible. From the first project all the way through to the last they have been excellent. We trust them fully.”
Jamie SmithDirector, Coate Water Care Ltd
Jamie's film coming soon
06 / What comes next

Further work.

  1. 01

    A new-build care home

    We're working with them on a full M&E and renewables package for a brand-new, bespoke care home, planned in from day one rather than added later.

  2. 02

    Air conditioning for existing homes

    We're also looking at adding air conditioning at some of their retrofit sites.

Next step / Define the brief

Have a portfolio of your own?